25 Aria Isle Dr · Lot 4 · The Woodlands, TXWhere Things Stand · 10/06/2026
Status as of Tue Oct 6, 2026, 3 pm

The piles are in. Proving they'll hold is the part that's left.

All 155 piles were installed by Oct 2, and Cantsink's engineer has certified them. Every one passed the twisting test. The soil borings found a weak layer that the twisting test can't see, so a pass doesn't settle it.

Done155 piles installed, final logs and a sealed letter delivered
SettledUnits, calibration, and pile 87 (it's half of a pair)
OpenA loose layer at 23–26 ft that most piles sit on or in
OpenRaw readings don't exist. The original field sheets are promised but not sent.
OpenJuan (Dunaway) has not signed off. Nothing gets poured until he does.
Soil layers and where the 155 piles stop A cross-section of the soil to 32 feet showing a firm crust at 18 to 21 feet, a loose layer at 23 to 26 feet, and five groups of piles stopping at different depths. Sandy / lean clay Organic silt (bad smell in B-1) Silty sand FIRM crust, N 23–27 LOOSE, N 10–11 (2025: N 8–9) Dense sand, N 33–42 (not everywhere) water ≈ 11½–15 ft 0 ft 4 ft 8 ft 12 ft 16 ft 20 ft 24 ft 28 ft 32 ft 30 78 21 5 21 piles
1

What was built

155piles, numbered 1–155, installed Sept 21 – Oct 2
22locations with two piles sharing a heavier load (44 piles)
58piles stop less than 20 ft down, the soil engineer's minimum
46were turned past the shaft's twisting rating of 7,091 ft-lb

Each pile is a steel screw. A machine turns it into the ground until the twisting force (torque) reaches a target. The harder it is to turn, the more weight it should carry. Cantsink's engineer, Dr. Souissi, signed a letter on Oct 5 saying every pile met its load.

Two pieces of evidence came in since then. Andrew Carter answered our questions today (Oct 6, 1:57 pm). The soil borings from Oct 5 show what the piles are actually sitting in.

2

What the borings found: a firm crust over a loose layer

On Oct 5, Quartet's driller bored two holes (B-1 and B-2) and counted hammer blows every few feet. More blows means firmer soil. Both holes show the same pattern: a firm layer around 18–21 ft, then a loose, wet layer at 23–26 ft (only 1–2 blows to start), then dense sand from about 28 ft.

This layer isn't new. Quartet's own 2025 borings logged the same "loose silty sand" at 23–25 ft. That's probably why their report set a 20-ft minimum depth.

DepthB-1 (Oct 5)B-2 (Oct 5)2025 boringsWhat it means
4–12 ftorganic silt 6–12 ft, bad smell, N 6–8sandy clay, N 8–18N 11–15Soft. Organic soil can corrode steel.
13–15 ftN 12N 8N 18–23Where the twelve 14-ft piles stop
18–20 ftN 23N 27N 18–20firm crust Most piles stop here
23–25 ft1-1-9 (N 10)2-1-10 (N 11)N 8, 9, 12loose Below the water table
28–30 ftN 33N 42B-3: N 15 to 40 ftdense here, not everywhere

N = hammer blows to drive the sampler 12 inches. Under ~10 is loose; 30+ is dense. These are the driller's handwritten field logs. Quartet's lab report hasn't arrived. The 2025 rig used an automatic hammer and the 2026 rig a manual one, so the numbers are close but not exactly comparable.

Where the holes are. I missed this earlier. The GPS points were on the logs all along, and Dmitri pointed it out by text at 1:28 pm. They put both holes about 30 ft south of the front-centre of the house, toward the street. Phone GPS is only good to about ±15 ft, and one digit on each log is unclear, so the coordinates can't tell you which piles the holes are next to. Ask Dmitri to mark both holes on the pile plan.
3

Why passing the twisting test doesn't settle it

Torque only measures how hard the soil right at the screw blade resisted turning. But a loaded blade pushes on soil 2–3 blade-widths below it, about 2–3½ ft for these 12–14″ blades. A pile that stops on the firm crust at 20 ft is pressing into the loose layer a few feet down. It can show full torque on the gauge and still settle more than expected.

We've already seen this once. In front of witnesses on 9/28, pile 12 was given a second turn after it passed. It sank through, and its torque dropped to about 2,300 below 26 ft.

Why a pile on a thin crust can pass the torque test and still settle Left: a helix resting on the firm crust stresses soil about two to three feet below it, which reaches the loose layer. Right: a helix in the dense sand below the loose layer has nothing weak beneath it. Stops on the crust (~20 ft) firm: torque reads high loose: carries the load Torque passes. The load still reaches weak soil. Goes through to dense sand (28 ft +) Nothing weak underneath.

The dashed outline is the soil the blade loads. Only a load test, which pushes on a pile and measures how far it sinks, can tell whether the crust is thick enough.

Where the blade stopsPilesRiskWhich piles
14–17 ft (above the crust)30soft soilTwelve at 14 ft: 18, 19, 21, 22, 23, 28, 122, 125, 126, 136, 137, 139
18–22 ft (on the crust)78loose layer 1–5 ft belowMost of the house. Dmitri's list: 46, 41, 42, 37, 71, 101, 104, 105
23–25 ft (in the loose layer)21highest1, 2, 5, 7, 9, 13, 14, 39, 43, 44, 45, 50, 52, 79, 87, 88, 89, 96, 131, 150, 152
26–27 ft (bottom edge)5lower11, 31, 138, 142, 143
28 ft and deeper21lowest4, 6, 8, 10, 12, 17, 27, 30, 58, 59, 61, 63, 80, 83, 92, 97, 116, 124, 127, 146, 154

"Net" depth = installed length minus what was cut off above ground. Cantsink writes "24′-3" meaning 24 ft installed, 3 ft cut off, so 21 ft in the ground. It isn't 24 ft 3 in. Dmitri's risk report read it the second way, so several of his depths are 3–4 ft too deep.

4

What Cantsink said today

Andrew Carter answered our seven questions at 1:57 pm. Juan, Scott, Dmitri, Murat and Yasamin were copied, plus Brittany and Sara Hayes. His answers, and whether each one holds up:

We askedAndrew saidVerdict
Recorded torque dataThe monitor can record every 2 seconds, but they don't turn it on. A printout after the fact is "not possible."gone No independent record exists. The handwritten logs are all there is.
Original field sheets"We will collect the field logs and send them over."promised Hold him to a date
Pile 17 (erased 2,717)Pulled out completely; a 10″ blade replaced with 12″ around 9/28–29.plausible Field sheet should show it
19 "No Cut" notes rewrittenA misunderstanding with the crew leader, fixed in the final logs. He explained what each note means.partly Field sheets will confirm
Pile 46 (7,003 vs video)The number on screen changes every second; both are above 60,000 lb.fair 7,096 is above the shaft rating, though
Pile 87 (6,618)It's half of a pair that shares 100,000 lb, so it needs only 5,556. "Needs no further work."resolved If Juan confirms 87/88 is a pair
The 9/24 10:47 am N·m pile"I'm not aware of the pile you are referring to." All piles were finished in ft-lb.unanswered Murat can identify it from the video
Burned bolt holes"Noted on the final logs."not answered The logs record no burned holes
Which piles are pairsListed all 22 pairs. 128/129 and 130/131 were doubled by mistake from staking, at no charge.answered
Single pile versus a pair of piles A single pile must prove 60,000 pounds. A pair shares a 100,000 pound requirement, 50,000 pounds each, so each pile in a pair only needs 5,556 foot-pounds. Single pile: 111 of them must prove 60,000 lb needs 6,667 ft-lb Pair: 22 locations, 44 piles share 100,000 lb, 50,000 each each needs 5,556 ft-lb

Andrew also says the piles' combined capacity beats the design total by about 500,000 lb. A house doesn't share load that way, though. Each pile carries the column or wall above it, so each one has to pass on its own.

5

Every pile passed its torque target, by a thin margin

Every final reading is above its target. But most are only a few percent over, and 46 are above what the shaft is rated to take (7,091). The couplings are the weak point; pile 145's coupling broke above 8,500.

single piles (111)piles in a pair (44)

Final torque in ft-lb, in 50 ft-lb steps. Single piles need 6,667; piles in a pair need 5,556. The only reading under 6,667 is pile 87, which is half of a pair. The monitor is accurate to about ±80 ft-lb.

6

What the paperwork still doesn't show

Settled

  • Units: the tablet switched to ft-lb on 9/24, between 10:47 am and 3:33 pm, and every final reading is in ft-lb.
  • Calibration: every tablet screen shows serial 638000EC (calibrated June 1, 2026), and RockSolid photographed the same number stamped on the rig.
  • RockSolid's 67 photographed readings: 47 match the final log, 20 are earlier readings that were later redone, none conflict.
  • Murat's own photos of the tablet match the final logs (one pile is off by 1).
  • Pile 87: covered as half of a pair, pending Juan.

Still open

  • Only 2 of 155 final readings were witnessed by the inspector: piles 110 and 111 on 9/26 (6,857.9 and 6,839.7, matching the log). Every other entry on RockSolid's forms is copied from Cantsink.
  • No raw data exists; the field sheets are promised.
  • Burned bolt holes appear in RockSolid's own 9/26 photo (three torch-cut holes in a cut shaft) and in Murat's photos, but not in the logs.
  • First attempts left off the final log: the original 10″ piles 110 and 111 (about 5,550 ft-lb before the units were fixed), 93, 94, 95 and the early pile 80. Pile 145's sheet says "snapped lead."
  • The N·m pile from 9/24 10:47 am is unidentified.
  • Piles 109 and 125 first appear on the final log.
  • Pile 12's original test isn't in the log.
7

What this could cost

ItemAmountBasis
Cantsink base (via Keystone)$86,700Proposal: piles to 17 ft
Depth over 17 ft, if billed$23,058 – $33,684$28/ft × 824 ft (net depth) to 1,203 ft (installed length). Only through a signed change order (Keystone addendum §7).
Two extra piles (128–131)$0Andrew: "will not be charged to anyone"
Load test on 2–3 pilesquote pendingQuartet hasn't quoted yet

Range only. Which depth Cantsink bills on (installed length or depth in the ground) isn't settled, and nothing has been invoiced.

→

So what do you do?

The next tab lays out the steps in order, with who owns each one and what has to be true before concrete is poured.

10 · What To Do
Prepared Oct 6, 2026 for 25 Aria Isle Dr, Lot 4. Sources: Cantsink final pile logs and Souissi certification (10/5); Andrew Carter email 10/6 1:57 pm; Ace GeoDrilling field logs B-1/B-2 (10/5, QGH-26-0221); Quartet QGH-25-0113 and Addendum 2; Steshenko risk report (10/6); RockSolid field reports 9/21–10/1; WhatsApp media; Keystone addendum. This page is a record review, not an engineering opinion. Acceptance belongs to Dunaway (Juan Gonzalez, PE).